Glen Elder Dam Spillway

Glenelder-project-47
Glenelder-9
Glenelder-project-36
Glenelder-27
Glenelder

Glen Elder Dam was constructed in the mid-twentieth century as part of a federal campaign to thwart extreme flooding of the Missouri River Basin. The dam in north central Kansas is a source for irrigation and municipal water, and it forms Waconda Lake, a popular recreational destination with 100 miles of shoreline.

With the goal of ensuring that the dam continues to protect and benefit the region, Ames began a three-year project in 2022 to repair the dam’s 644-foot-wide concrete spillway.

Crews are replacing 98 spillway panels, which equates to 13,200 cubic yards of self-batched and placed concrete. The project requires the removal of aging concrete, existing drainage material, and pipe, along with rock excavation and pipe trench grading.

Ames hit several milestones in the project’s first year, including the construction of temporary roads, setting up the batch plant, and developing the process to produce a consistent batch of concrete that meets owner requirements. In Year 2, crews removed existing concrete, placed high-quality concrete, installed piping, and placed some of the project’s spillway panels.

Learn more: Bureau of Reclamation

Markets: Federal, Water Resources, Dams

Location: Glen Elder, Kansas

Completion: In progress

Project Owner: U.S. Bureau of Reclamation

Services:

  • Concrete production
  • Rock excavation
  • Pipe trench grading

Details:

  • Removing existing concrete, drainage material, and pipe
  • Replacing 98 spillway panels